[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124523":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124523,792,1,"单选题","在起吊桥梁构件时，吊绳与构件夹角小于（ ）时应设置吊架或吊装扁担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30°",false,{"key":16,"text":17,"correct":14},"B","45°",{"key":19,"text":20,"correct":21},"C","60°",true,{"key":23,"text":24,"correct":14},"D","75°","装配式桥梁构件移运、吊装时的吊点位置应按设计规定或根据计算决定。吊装时构件的吊环应顺直，吊绳与起吊构件的交角小于60°时，应设置吊架或吊装扁担，尽量使吊环垂直受力。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]