[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1124519,792,1,"单选题","预应力混凝土构件吊装时，其孔道水泥浆的强度不应低于构件的设计要求，如设计无要求，一般不低于（ ）MPa。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":14},"C","25",{"key":22,"text":23,"correct":24},"D","30",true,"本题主要考查的是装配式梁（板）的安装。装配式桥梁构件在脱底模、移运、堆放和吊装就位时，混凝土的强度不应低于设计要求的吊装强度，一般不应低于设计强度的75%；预应力混凝土构件吊装时，其孔道水泥浆的强度不应低于构件设计要求，如设计无要求时，一般不低于30MPa。吊装前应验收合格。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]