[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124514,792,1,"单选题","下列关于沉入桩施工的说法中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在砂土地基沉桩困难时，可采用射水辅助沉桩",false,{"key":16,"text":17,"correct":14},"B","当桩数较多时，沉桩顺序宜由中间向两端或向四周施工",{"key":19,"text":20,"correct":21},"C","在斜坡地带沉桩时，应先沉坡脚，后沉坡顶的桩",true,{"key":23,"text":24,"correct":14},"D","当桩埋置有深浅之别时，宜先沉深的，后沉浅的桩","本题考查的是沉入桩基础。选项C的正确说法“在斜坡地带沉桩时，应先沉坡顶，后沉坡脚的桩，以免桩互相干扰”。沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计高程，宜先深后浅；根据桩的规格，宜先大后小，先长后短。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]