[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1124482,792,1,"单选题","先张法预应力施工中，放张预应力筋时应（ ）地放张。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分阶段、对称、交错",true,{"key":16,"text":17,"correct":18},"B","分阶段、顺序",false,{"key":20,"text":21,"correct":18},"C","一次性、对称、交错",{"key":23,"text":24,"correct":18},"D","一次性、顺序","放张预应力筋时混凝土强度必须符合设计要求，设计未规定时，不得低于强度设计值的75%。放张顺序应符合设计要求，设计未规定时，应分阶段、对称、交错地放张。放张前，应将限制位移的模板拆除。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]