[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124475,792,1,"单选题","在空气湿度小于40%的情况下，进行预应力筋的安装，超过（ ）d应对预应力筋采取防锈措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":21},"C","20",true,{"key":23,"text":24,"correct":14},"D","21","本题考查的是预应力张拉施工。预应力筋穿束后至孔道灌浆完成应控制在下列时间内，否则应对预应力筋采取防锈措施：（1）空气湿度大于70%或盐分过大时，7天；（2）空气湿度40%～70%，15天；（3）空气湿度小于40%时，20天。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]