[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-791-4":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":595},{"id":5,"name":6,"category":7,"favorite":8},791,"二建矿业工程实务","建筑工程",0,4,50,1681,[13,34,46,58,70,82,94,103,115,127,139,151,163,175,187,199,207,219,231,243,252,264,276,288,300,308,320,332,341,353,361,373,385,397,409,421,433,445,457,469,481,491,503,515,527,539,549,561,571,583],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},1122846,1,"单选题","水冲法沉桩一般是边冲水边打桩，当沉桩至最后（ ）时停止冲水，用锤击至规 定标高。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","0, 5m",false,{"key":24,"text":25,"correct":22},"B","1m",{"key":27,"text":28,"correct":29},"C","1 ~2m",true,{"key":31,"text":32,"correct":22},"D","2~3m","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},1122847,"关于人工挖孔灌注桩的特点，说法错误的是（）。",[38,40,42,44],{"key":20,"text":39,"correct":29},"单桩承载力高，结构受力明确，沉降量大",{"key":24,"text":41,"correct":22},"可直接检查桩直径、垂直度、持力层情况，桩的质量可靠",{"key":27,"text":43,"correct":22},"施工机具设备简单，工艺操作简单，占场地小",{"key":31,"text":45,"correct":22},"施工无振动、无噪声、无环境污染，对周边建筑无影响",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},1122848,"用锤击法打桩时，最大落距（）。",[50,52,54,56],{"key":20,"text":51,"correct":29},"不宜大于1m",{"key":24,"text":53,"correct":22},"不宜小于1m",{"key":27,"text":55,"correct":22},"不宜大于2m",{"key":31,"text":57,"correct":22},"不宜小于2m",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":27,"analysis":33},1122849,"关于砂和砂石地基，以下说法错误的是（）。",[62,64,66,68],{"key":20,"text":63,"correct":22},"砂和砂石地基采用砂或砂砾石(碎石)混合物，经分层夯(压)实，作为地基的持力层，提高基础下部地基强度，并通过垫层的压力扩散作业，降低地基的压应力，减少变形量，同时垫层可起到排水作业，地基土中孔隙水可通过垫层快速排出，能加速下部土层的沉降和固结",{"key":24,"text":65,"correct":22},"砂和砂石地基具有应用范围广泛；不用水泥、石材；由于砂颗粒大，可防止地下水因毛细作用上升，地基不受冻结影响；能在施工期间完成沉陷；用机械或人工都可使地基密实，施工工艺简单，可缩短工期，降低造价等特点",{"key":27,"text":67,"correct":29},"适用于处理5.0m 以内的软弱、透水性强的黏性土地基，包括淤泥、游泥质土",{"key":31,"text":69,"correct":22},"不宜用于加固湿陷性黄土地基及渗透系数小的黏性土地基",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},1122850,"关于土桩和灰土桩，以下说法错误的是（）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"土桩和灰土桩挤密地基是由桩间挤密土和填夯的桩体组成的人工“ 复合地基”",{"key":24,"text":77,"correct":29},"适用于处理地下水位以上，深度10~25 m的湿陷性黄土或人工填土地基",{"key":27,"text":79,"correct":22},"土桩主要适用于消除湿陷性黄土地基的湿陷性，灰土桩主要适用于提高人工填土地基的承载力",{"key":31,"text":81,"correct":22},"地下水位以下或含水量超过2 5 %的土，不宜采用",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":27,"analysis":33},1122851,"加固各种成因的饱和状土(如淤泥），可增加软土地基的承载力的基础是（）。",[86,88,90,92],{"key":20,"text":87,"correct":22},"灰土桩",{"key":24,"text":89,"correct":22},"水泥粉煤灰碎石桩",{"key":27,"text":91,"correct":29},"深层搅拌法桩",{"key":31,"text":93,"correct":22},"碎石桩",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":20,"analysis":33},1122853,"用于地下水位以上，深度5~15m湿陷性黄土或人工填土的地基是（ ）。",[98,99,100,102],{"key":20,"text":87,"correct":29},{"key":24,"text":89,"correct":22},{"key":27,"text":101,"correct":22},"深层搅拌法施工",{"key":31,"text":93,"correct":22},{"id":104,"libraryId":5,"type":15,"typeLabel":16,"stem":105,"options":106,"answer":27,"analysis":33},1122855,"在灰土桩挤密地基中，只占地基面积约20%的灰土桩可以承担总荷载的（ ）。",[107,109,111,113],{"key":20,"text":108,"correct":22},"20%",{"key":24,"text":110,"correct":22},"40%",{"key":27,"text":112,"correct":29},"50%",{"key":31,"text":114,"correct":22},"60%",{"id":116,"libraryId":5,"type":15,"typeLabel":16,"stem":117,"options":118,"answer":31,"analysis":33},1122858,"关于独立基础，以下说法错误的是（）。",[119,121,123,125],{"key":20,"text":120,"correct":22},"单独基础是柱子基础的主要类型。它所用材料根据柱的材料和荷载大小而定，常采用砖、石、混凝土和钢筋混凝土等。",{"key":24,"text":122,"correct":22},"现浇柱下钢筋混凝土基础的截面可做成阶梯形和锥形，预制柱下的基础一般做成杯形基础，等柱子插入杯口后，将柱子临时支撑，然后用细石混凝土将柱周围的缝隙填实",{"key":27,"text":124,"correct":22},"墙下单独基础是当上层土质松软，而在不深处有较好的土层时，为了节约基础材料和减少开挖土方量而采用的一种基础形式。砖墙砌筑在单独基础上边的钢筋混凝土地梁上。",{"key":31,"text":126,"correct":29},"地梁跨度一般为6~10 m",{"id":128,"libraryId":5,"type":15,"typeLabel":16,"stem":129,"options":130,"answer":31,"analysis":33},1122859,"关于地下连续墙的缺点，以下说法错误的是（）。",[131,133,135,137],{"key":20,"text":132,"correct":22},"每段连续墙之间的接头质量较难控制，往往容易形成结构的薄弱点。",{"key":24,"text":134,"correct":22},"施工技术要求高，无论是造槽机械选择、槽体施工、泥浆下浇筑混凝土、接头、泥浆处理等环节，均应处理得当，不容疏漏",{"key":27,"text":136,"correct":22},"墙面虽可保证垂直度，但比较粗糙，尚须加工处理或做衬壁",{"key":31,"text":138,"correct":29},"可将地下连续墙与“ 逆作法”施工结合，形成一种深基础多层地下室施工的有效方法",{"id":140,"libraryId":5,"type":15,"typeLabel":16,"stem":141,"options":142,"answer":20,"analysis":33},1122860,"地下连续墙施工各工序先后顺序是（）。",[143,145,147,149],{"key":20,"text":144,"correct":29},"导墙—分段成槽—泥浆护壁—浇筑混凝土",{"key":24,"text":146,"correct":22},"导墙—分段成槽—掉放接头管—浇筑混凝土",{"key":27,"text":148,"correct":22},"导墙—分段挖土成槽—注入泥浆—排渣",{"key":31,"text":150,"correct":22},"分段成槽—导墙—吸泥清底—浇筑混凝土",{"id":152,"libraryId":5,"type":15,"typeLabel":16,"stem":153,"options":154,"answer":31,"analysis":33},1122861,"下列工程材料，不可用作地下连续墙墙体材料的是（）。",[155,157,159,161],{"key":20,"text":156,"correct":22},"钢筋混凝土",{"key":24,"text":158,"correct":22},"素混凝土",{"key":27,"text":160,"correct":22},"黏土",{"key":31,"text":162,"correct":29},"砂土",{"id":164,"libraryId":5,"type":15,"typeLabel":16,"stem":165,"options":166,"answer":27,"analysis":33},1122863,"关于明排水法，以下说法错误的是（）。",[167,169,171,173],{"key":20,"text":168,"correct":22},"明排水法是在基坑开挖过程中，在坑底设置集水坑，并沿坑底周围或中央开挖排水沟，使水流入集水坑，然后用水栗抽走。抽出的水应及时排除，以防倒流。所用的水泵主要有离心泵、潜水泵和软抽水泵。",{"key":24,"text":170,"correct":22},"明排水法由于设备简单和排水方便，因而被普遍采用。宜用于粗粒土层，也用于渗水量小的黏土层。但当土为细砂和粉砂时，地下水渗出会带走细粒，发生流砂现象，导致边坡坍塌、坑底涌砂，难以施工，此时应采用井点降水法",{"key":27,"text":172,"correct":29},"集水坑应设置在基础范围以外，地下水的上游。根据地下水量大小、基坑平面形状及水泵能力，集水坑每隔30~50 m 设置一个",{"key":31,"text":174,"correct":22},"集水坑的直径或宽度，一般为0.6~0 . 8 m。其深度，随着挖土的加深而加深，要保持低于挖土面0.7~1 . 0 m。坑壁可用竹、木或钢筋笼等简易加固。当基础挖至设计标高后，坑底应低于基础底面标高1~2 m，并铺设碎石滤水层，以免在抽水时间较长时将泥砂抽出，并防止坑底的土被扰动",{"id":176,"libraryId":5,"type":15,"typeLabel":16,"stem":177,"options":178,"answer":31,"analysis":33},1122864,"当降水深度大于15m，为了满足降水要求，宜选用（）降水方法。",[179,181,183,185],{"key":20,"text":180,"correct":22},"轻型井点",{"key":24,"text":182,"correct":22},"喷射井点",{"key":27,"text":184,"correct":22},"管井井点",{"key":31,"text":186,"correct":29},"深井井点",{"id":188,"libraryId":5,"type":15,"typeLabel":16,"stem":189,"options":190,"answer":20,"analysis":33},1122865,"宜采用管井井点降水的情况是（）。",[191,193,195,197],{"key":20,"text":192,"correct":29},"土的渗透系数大、地下水量大的土层中",{"key":24,"text":194,"correct":22},"基坑面积较大时",{"key":27,"text":196,"correct":22},"当降水深度超过15m时",{"key":31,"text":198,"correct":22},"当基坑较深而地下水位又较高时",{"id":200,"libraryId":5,"type":15,"typeLabel":16,"stem":201,"options":202,"answer":20,"analysis":33},1122866,"当基坑宽度为6m，需要降水的深度为9m，拟采用喷射井点进行降水，井点的布 置的最经济的方式为（ ）。 A.单排布置 双排布置 C. U形布置 D.环形布置",[203,204,205,206],{"key":20,"text":20,"correct":29},{"key":24,"text":24,"correct":22},{"key":27,"text":27,"correct":22},{"key":31,"text":31,"correct":22},{"id":208,"libraryId":5,"type":15,"typeLabel":16,"stem":209,"options":210,"answer":27,"analysis":33},1122867,"关于喷射井点面的平面布置，说法错误的是（）。",[211,213,215,217],{"key":20,"text":212,"correct":22},"当基坑宽度小于等于10m时，井点可作单排布置",{"key":24,"text":214,"correct":22},"当基坑宽度大于10m时，可作双排布置",{"key":27,"text":216,"correct":29},"当基坑面积较小时，宜采用环形布置",{"key":31,"text":218,"correct":22},"当土方施工机械需要进出基坑时，也可采用U形布置",{"id":220,"libraryId":5,"type":15,"typeLabel":16,"stem":221,"options":222,"answer":24,"analysis":33},1122868,"具有支护和挡土双重功能的基坑支护形式是（）。",[223,225,227,229],{"key":20,"text":224,"correct":22},"横撑式支撑",{"key":24,"text":226,"correct":29},"重力式支护结构",{"key":27,"text":228,"correct":22},"板式支护结构",{"key":31,"text":230,"correct":22},"喷锚支护",{"id":232,"libraryId":5,"type":15,"typeLabel":16,"stem":233,"options":234,"answer":24,"analysis":33},1122869,"关于土钉支护的说法，正确的是（）。",[235,237,239,241],{"key":20,"text":236,"correct":22},"土钉支护适用于水位高的地区，土层为黏土、砂土和粉土",{"key":24,"text":238,"correct":29},"土钉支护工艺中喷射混凝土在高压空气作用下，高速喷向喷面，在喷层与土层 间产生嵌固效应，从而改善了边坡的受力条件，有效地保证边坡稳定",{"key":27,"text":240,"correct":22},"土钉支护是新兴的挡土支护技术，最先用于基础深基坑支护，20世纪90年代 在隧道及治理滑坡中应用",{"key":31,"text":242,"correct":22},"土钉支护工艺，应先喷后锚，严禁先锚后喷",{"id":244,"libraryId":5,"type":15,"typeLabel":16,"stem":245,"options":246,"answer":31,"analysis":33},1122870,"适用于水位低的地区，或能保证降水在基坑面以下，土层为黏土、砂土、粉土， 基坑深度在12m左右的基坑支护方式是（）。",[247,248,249,250],{"key":20,"text":224,"correct":22},{"key":24,"text":226,"correct":22},{"key":27,"text":228,"correct":22},{"key":31,"text":251,"correct":29},"土钉支护",{"id":253,"libraryId":5,"type":15,"typeLabel":16,"stem":254,"options":255,"answer":31,"analysis":33},1122873,"关于地下连续墙施工中采用泥浆的主要作用，错误的是（）。",[256,258,260,262],{"key":20,"text":257,"correct":22},"固壁",{"key":24,"text":259,"correct":22},"携砂",{"key":27,"text":261,"correct":22},"冷却和润滑",{"key":31,"text":263,"correct":29},"堵水",{"id":265,"libraryId":5,"type":15,"typeLabel":16,"stem":266,"options":267,"answer":24,"analysis":33},1122874,"关于SMW定位、钻孔施工，以下说法错误的是（）。",[268,270,272,274],{"key":20,"text":269,"correct":22},"在开挖的工作沟槽两侧铺设导向定位型钢或定位辅助线，按设计要求在导向定位型钢或定位辅助线上做出钻孔位置和H 型钢的插入位置。根据确定的位置严格将钻机桩架移动就位。",{"key":24,"text":271,"correct":29},"开钻前应用水平尺将平台调平，并调直机架，确保机架垂直度不小于1% 。并在成孔、提升过程中经常检査平台水平度和机架垂直度，确保成桩垂直度不大于3%",{"key":27,"text":273,"correct":22},"为控制钻管下钻深度达标，利用钻管和桩架相对错位原理，在钻管上划出钻孔深度的标尺线，严格控制下钻、提升的速度和深度",{"key":31,"text":275,"correct":22},"下钻、提升速度应与注浆泵的泵量相适应，同时下钻速度不大于100cm\u002Fmin，提升速度不大于180c m \u002F m i n并至少复拌一次以上",{"id":277,"libraryId":5,"type":15,"typeLabel":16,"stem":278,"options":279,"answer":20,"analysis":33},1122875,"钢井架结构的五大组成部分主要是头部、立架、斜架、井口支撑梁和（）。",[280,282,284,286],{"key":20,"text":281,"correct":29},"斜架基础",{"key":24,"text":283,"correct":22},"立架基础",{"key":27,"text":285,"correct":22},"天轮托架",{"key":31,"text":287,"correct":22},"卸载曲轨",{"id":289,"libraryId":5,"type":15,"typeLabel":16,"stem":290,"options":291,"answer":27,"analysis":33},1122876,"用来承受大部分的提升钢丝绳荷载，并维持井架的整体稳定性的钢井架结构构件是（ ）。",[292,294,296,298],{"key":20,"text":293,"correct":22},"头部",{"key":24,"text":295,"correct":22},"立架",{"key":27,"text":297,"correct":29},"斜架",{"key":31,"text":299,"correct":22},"井口支撑梁",{"id":301,"libraryId":5,"type":15,"typeLabel":16,"stem":302,"options":303,"answer":24,"analysis":33},1122877,"钢结构井架中，构成井架直立的那一部分空间结构，用来固定地面以上的罐道、 卸载曲轨等，并承受头部下传的荷载的部分是（）。",[304,305,306,307],{"key":20,"text":293,"correct":22},{"key":24,"text":295,"correct":29},{"key":27,"text":297,"correct":22},{"key":31,"text":299,"correct":22},{"id":309,"libraryId":5,"type":15,"typeLabel":16,"stem":310,"options":311,"answer":31,"analysis":33},1122878,"关于井架的安装，以下说法错误的是（）。",[312,314,316,318],{"key":20,"text":313,"correct":22},"井口组装就地起立旋转法：在井口附近平整场地组装井架；在井口中心组装诡杆，用吊车抬起桅杆头部，用稳车竖立桅杆；利用桅杆和井架底部支撑铰链采用大旋转法旋转就位；利用井架放倒桅杆；利用立架采用滑移提升法起吊斜架；最后拆除滑轮组和桅杆；安装需要拉力较大，使用设备较多。该方法目前主要适用于井口场地平整、宽敞，井架的重量大，高度较高的情况。",{"key":24,"text":315,"correct":22},"利用吊车安装法：利用吊车吊起杆件或部件在井口进行安装；可节省时间、安装工序简单；使用设备较少。该方法目前主要适用于井口场地受限的中小型井架",{"key":27,"text":317,"correct":22},"井口外组装整体滑移安装法：在井口外组装井架；用千斤顶抬起井架，使井架底座高于井口；利用铺设的滑道，用稳车和千不拉滑移井架至井口设计位置。这种方法主要适用于场地受限，占用井口工期较少的情况",{"key":31,"text":319,"correct":29},"大模板施工方法：井架构筑物整体性好，预埋件易于固定，确保了钢筋保护层；井架按楼层划分施工段，为安装创造了较好条件；充分发挥地面拼装的优越性，大大改善了作业环境，减少了高空作业，节省劳力，降低了劳动强度；采用泵送工艺，实现了混凝土机械化施工配套作业线。但是，施工现场需有较大的专用场地，供预制、拼装和堆放大模板；同时需要一定的机械设备，进行吊装作业和满足快速施工；此外，混凝土输送距离长，必须保证流态混凝土连续供料以及塔壁和柱深层处混凝土的浇筑质量",{"id":321,"libraryId":5,"type":15,"typeLabel":16,"stem":322,"options":323,"answer":24,"analysis":33},1122879,"井口场地受限制的中小型井架的安装方法是（）。",[324,326,328,330],{"key":20,"text":325,"correct":22},"井口组装就地起立旋转法",{"key":24,"text":327,"correct":29},"利用吊车安装法",{"key":27,"text":329,"correct":22},"井口外组装整体滑移的安装法",{"key":31,"text":331,"correct":22},"平行吊装法",{"id":333,"libraryId":5,"type":15,"typeLabel":16,"stem":334,"options":335,"answer":27,"analysis":33},1122880,"吊装中小型井架时，吊装现场场地受限，且工期要求紧，适合于选用的吊装方法 是（ ）。",[336,337,338,340],{"key":20,"text":325,"correct":22},{"key":24,"text":327,"correct":22},{"key":27,"text":339,"correct":29},"井口外组装整体滑移的安装法 .",{"key":31,"text":331,"correct":22},{"id":342,"libraryId":5,"type":15,"typeLabel":16,"stem":343,"options":344,"answer":20,"analysis":33},1122882,"当井塔施工工期要求紧迫，企业技术、管理素质、施工装备好，井塔上又无悬挑 梁时，应积极选用（）施工方法。",[345,347,349,351],{"key":20,"text":346,"correct":29},"滑模施工方法",{"key":24,"text":348,"correct":22},"大模板施工方法",{"key":27,"text":350,"correct":22},"爬模施工方法",{"key":31,"text":352,"correct":22},"预建整体平移施工方法",{"id":354,"libraryId":5,"type":15,"typeLabel":16,"stem":355,"options":356,"answer":31,"analysis":33},1122883,"可以缩短井塔施工和提升设备安装占用井口的时间，解决井口矿建、土建和机电 安装三类工程的矛盾，且可缩短建井总工期，加快建井速度，这种施工方法是（）。",[357,358,359,360],{"key":20,"text":346,"correct":22},{"key":24,"text":348,"correct":22},{"key":27,"text":350,"correct":22},{"key":31,"text":352,"correct":29},{"id":362,"libraryId":5,"type":15,"typeLabel":16,"stem":363,"options":364,"answer":27,"analysis":33},1122885,"预应力混凝土筒体施工，在施加预应力完成后，对钢丝束端部连同锚具一道用 ()封闭。",[365,367,369,371],{"key":20,"text":366,"correct":22},"环氧树脂",{"key":24,"text":368,"correct":22},"水泥砂浆",{"key":27,"text":370,"correct":29},"膨胀性高强度等级细实混凝土",{"key":31,"text":372,"correct":22},"硫磺胶泥",{"id":374,"libraryId":5,"type":15,"typeLabel":16,"stem":375,"options":376,"answer":20,"analysis":33},1122886,"钢筋混凝土结构施工时，使用的模板属于组合式模板的是（）。",[377,379,381,383],{"key":20,"text":378,"correct":29},"钢框竹胶合板模板",{"key":24,"text":380,"correct":22},"滑动模板",{"key":27,"text":382,"correct":22},"爬升模板",{"key":31,"text":384,"correct":22},"模壳",{"id":386,"libraryId":5,"type":15,"typeLabel":16,"stem":387,"options":388,"answer":20,"analysis":33},1122887,"采用冷拉方法调直HPB335级钢筋时，冷拉率不宜大于（ ）。",[389,391,393,395],{"key":20,"text":390,"correct":29},"1%",{"key":24,"text":392,"correct":22},"4%",{"key":27,"text":394,"correct":22},"5%",{"key":31,"text":396,"correct":22},"10%",{"id":398,"libraryId":5,"type":15,"typeLabel":16,"stem":399,"options":400,"answer":20,"analysis":33},1122888,"为使混凝土不发生离析现象，当浇筑高度超过（）m时，应采用串筒、溜管或 振动溜管使混凝土下落。",[401,403,405,407],{"key":20,"text":402,"correct":29},"3",{"key":24,"text":404,"correct":22},"4",{"key":27,"text":406,"correct":22},"5",{"key":31,"text":408,"correct":22},"6",{"id":410,"libraryId":5,"type":15,"typeLabel":16,"stem":411,"options":412,"answer":27,"analysis":33},1122889,"混凝土养护的目的是为混凝土（）创造必要的湿度、温度条件。",[413,415,417,419],{"key":20,"text":414,"correct":22},"初凝",{"key":24,"text":416,"correct":22},"终凝",{"key":27,"text":418,"correct":29},"硬化",{"key":31,"text":420,"correct":22},"固化",{"id":422,"libraryId":5,"type":15,"typeLabel":16,"stem":423,"options":424,"answer":20,"analysis":33},1122891,"砌块施工工艺的步骤为（ ）。",[425,427,429,431],{"key":20,"text":426,"correct":29},"铺灰——砌块吊装就位——校正——灌浆——镶砖",{"key":24,"text":428,"correct":22},"铺灰——砌块吊装就位——灌浆——校正——镶砖",{"key":27,"text":430,"correct":22},"铺灰——砌块吊装就位——校正——镶砖——灌浆",{"key":31,"text":432,"correct":22},"铺灰——镶砖——砌块吊装就位——校正——灌浆",{"id":434,"libraryId":5,"type":15,"typeLabel":16,"stem":435,"options":436,"answer":31,"analysis":33},1122892,"砌块的吊装一般按施工段依次进行，一般以一个或两个单元为一个施工段，进行 分段流水施工，其次序为（）。",[437,439,441,443],{"key":20,"text":438,"correct":22},"先外后内，先远后近，先上后下",{"key":24,"text":440,"correct":22},"先外后内，先近后远，先下后上",{"key":27,"text":442,"correct":22},"先内后外，先远后近，先下后上",{"key":31,"text":444,"correct":29},"先外后内，先远后近，先下后上",{"id":446,"libraryId":5,"type":15,"typeLabel":16,"stem":447,"options":448,"answer":24,"analysis":33},1122893,"一般而言，焊接规范最主要的是（）的选择。",[449,451,453,455],{"key":20,"text":450,"correct":22},"焊接的道数",{"key":24,"text":452,"correct":29},"焊接电流与焊条直径",{"key":27,"text":454,"correct":22},"焊接速度与焊缝长度",{"key":31,"text":456,"correct":22},"焊接的层数",{"id":458,"libraryId":5,"type":15,"typeLabel":16,"stem":459,"options":460,"answer":27,"analysis":33},1122895,"根据起重机械的使用特点，()适用于单件大、中型设备、构件的吊装。",[461,463,465,467],{"key":20,"text":462,"correct":22},"门式桅杆起重机",{"key":24,"text":464,"correct":22},"塔式起重机",{"key":27,"text":466,"correct":29},"自行式起重机",{"key":31,"text":468,"correct":22},"独脚桅杆起重机",{"id":470,"libraryId":5,"type":15,"typeLabel":16,"stem":471,"options":472,"answer":27,"analysis":33},1122896,"结构安装工程中，不适用于需要经常移动作业场地工程施工的起重机类型是（）。",[473,475,477,479],{"key":20,"text":474,"correct":22},"电动式汽车起重机",{"key":24,"text":476,"correct":22},"液压式汽车起重机",{"key":27,"text":478,"correct":29},"电动式履带起重机",{"key":31,"text":480,"correct":22},"液压式履带起重机",{"id":482,"libraryId":5,"type":15,"typeLabel":16,"stem":483,"options":484,"answer":27,"analysis":33},1122897,"履带式起重机属于（）起重机的一种。",[485,487,488,489],{"key":20,"text":486,"correct":22},"桅杆式起重机",{"key":24,"text":464,"correct":22},{"key":27,"text":466,"correct":29},{"key":31,"text":490,"correct":22},"轮胎式起重机",{"id":492,"libraryId":5,"type":15,"typeLabel":16,"stem":493,"options":494,"answer":24,"analysis":33},1122898,"选择起重机时应使起重机吊装荷载（）被吊装构件的重量。",[495,497,499,501],{"key":20,"text":496,"correct":22},"小于",{"key":24,"text":498,"correct":29},"大于",{"key":27,"text":500,"correct":22},"等于",{"key":31,"text":502,"correct":22},"不等于",{"id":504,"libraryId":5,"type":15,"typeLabel":16,"stem":505,"options":506,"answer":27,"analysis":33},1122899,"在已知被吊装构件的就位高度、吊装高度和幅度的情况下，可査起重机的特性曲 线，确定其（）。",[507,509,511,513],{"key":20,"text":508,"correct":22},"起吊重量",{"key":24,"text":510,"correct":22},"行走速度",{"key":27,"text":512,"correct":29},"臂长",{"key":31,"text":514,"correct":22},"起重臂倾角",{"id":516,"libraryId":5,"type":15,"typeLabel":16,"stem":517,"options":518,"answer":27,"analysis":33},1122900,"拌制混凝土时宜采用的砂子是（）。",[519,521,523,525],{"key":20,"text":520,"correct":22},"山砂",{"key":24,"text":522,"correct":22},"海砂",{"key":27,"text":524,"correct":29},"河砂",{"key":31,"text":526,"correct":22},"人工砂",{"id":528,"libraryId":5,"type":15,"typeLabel":16,"stem":529,"options":530,"answer":27,"analysis":33},1122901,"在搅拌第一盘混凝土时，考虑到筒壁上的砂浆损失，（）用量应按配合比规定 减半。",[531,533,535,537],{"key":20,"text":532,"correct":22},"水泥",{"key":24,"text":534,"correct":22},"砂",{"key":27,"text":536,"correct":29},"石子",{"key":31,"text":538,"correct":22},"水",{"id":540,"libraryId":5,"type":15,"typeLabel":16,"stem":541,"options":542,"answer":24,"analysis":33},1122902,"混凝土配制时，其水泥用量的允许偏差不得超过（）。",[543,544,546,548],{"key":20,"text":390,"correct":22},{"key":24,"text":545,"correct":29},"2%",{"key":27,"text":547,"correct":22},"3%",{"key":31,"text":392,"correct":22},{"id":550,"libraryId":5,"type":15,"typeLabel":16,"stem":551,"options":552,"answer":20,"analysis":33},1122903,"钢结构焊接接头缺陷中，属于外部缺陷的是（）。",[553,555,557,559],{"key":20,"text":554,"correct":29},"咬肉",{"key":24,"text":556,"correct":22},"裂纹",{"key":27,"text":558,"correct":22},"未焊透",{"key":31,"text":560,"correct":22},"夹渣",{"id":562,"libraryId":5,"type":15,"typeLabel":16,"stem":563,"options":564,"answer":31,"analysis":33},1122904,"钢结构焊接接头缺陷中，属于内部缺陷的是（）。",[565,566,568,570],{"key":20,"text":554,"correct":22},{"key":24,"text":567,"correct":22},"气孔",{"key":27,"text":569,"correct":22},"焊瘤",{"key":31,"text":560,"correct":29},{"id":572,"libraryId":5,"type":15,"typeLabel":16,"stem":573,"options":574,"answer":31,"analysis":33},1122905,"钢结构焊接的主要参数不包括（）。",[575,577,579,581],{"key":20,"text":576,"correct":22},"焊接电压",{"key":24,"text":578,"correct":22},"焊接速度",{"key":27,"text":580,"correct":22},"焊缝长度",{"key":31,"text":582,"correct":29},"焊接时间",{"id":584,"libraryId":5,"type":15,"typeLabel":16,"stem":585,"options":586,"answer":24,"analysis":33},1122906,"钢结构焊接存在焊瘤属于（）。",[587,589,591,593],{"key":20,"text":588,"correct":22},"外观质量",{"key":24,"text":590,"correct":29},"外观缺陷",{"key":27,"text":592,"correct":22},"内在质量",{"key":31,"text":594,"correct":22},"内部缺陷",[596,599,602,605,608,611],{"id":15,"name":597,"category":7,"favorite":598},"领导干部任职前廉政法规知识测试题",92,{"id":600,"name":601,"category":7,"favorite":15},595,"建筑结构与设备",{"id":603,"name":604,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":606,"name":607,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":609,"name":610,"category":7,"favorite":8},534,"BIM工程师",{"id":612,"name":610,"category":7,"favorite":8},535]