[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124433":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124433,791,2,"多选题","矿业工程项目施工队的组织形式包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","井筒掘进队",false,{"key":16,"text":17,"correct":14},"B","巷道掘进队",{"key":19,"text":20,"correct":14},"C","安装工作队",{"key":22,"text":23,"correct":24},"D","专业掘进队",true,{"key":26,"text":27,"correct":24},"E","综合掘进队","DE","P120-122 对于立井井筒掘砌施工来说，一般施工队的劳动组织形式分为两种:一种是综合掘进队组织形式，综合掘进队是将井巷工程施工需要的主要工种（掘进、支护）以及辅助工种（机电维护、运输）组织在一个掘进队内。这种掘进队形式通常是一个项目部承担一个井筒时采用比较适宜，可以很好地协调沟通，避免推诿扯皮。掘进队下面可以分成几个掘进班组、支护班组、运输班组、机电维护班组等。另一种是专业掘进队组织形式。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]