[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124430":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124430,791,2,"多选题","目前，矿业工程项目的施工组织设计可分为（ ）等。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","矿区施工组织总设计",true,{"key":16,"text":17,"correct":14},"B","单项工程施工组织设计",{"key":19,"text":20,"correct":14},"C","单位工程施工组织设计",{"key":22,"text":23,"correct":24},"D","井巷工程施工组织设计",false,{"key":26,"text":27,"correct":24},"E","土建工程施工组织设计","ABC","P104-108 据拟建项目规模大小、结构特点、技术繁简程度和施工条件，应相应编制涉及内容深度和范围不同的施工组织设计。目前，矿业工程项目的施工组织设计照项目进度的不同阶段，可分为:建设项目（如矿区）施工组织总体设计、单项工程施工组织设计、单位工施工组织设计（技术措施），有时还需要编制特殊工程施工组织设计、季节性技术措施设计以及年度施工组织设计等。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]