[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124428":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124428,791,2,"多选题","矿山井巷工程过期能工安排中,对于井下三期工程煤巷工程量大。施工速度要求高,对提升能力有较高要求的矿井提升改装方案有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","风井临时改装箕斗提升",true,{"key":16,"text":17,"correct":18},"B","副井临时改装箕斗提升",false,{"key":20,"text":21,"correct":14},"C","主井临时改装罐笼和箕斗混合提升",{"key":23,"text":24,"correct":18},"D","雨井临时改装罐笼和斗混合提升",{"key":26,"text":27,"correct":14},"E","风井临时改装罐笼和箕斗混合提升","ACE","P112-114 随着井下开拓工程量的增大，特别是煤巷开拓工程量大幅度增加，施工速度提升很快，对提升能力提出了更高的需求。现在有一种新的改装方案，是利用风井或主井箕斗和罐笼合改绞，同时布置箕斗和罐笼，以大幅增加提升能力，给井下采区巷道的快速开拓提供保障。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]