[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124421":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124421,791,2,"多选题","施工准备工作的具体内容总体上应包括技术准备、工程准备、（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对外协作",true,{"key":16,"text":17,"correct":18},"B","编制单项工程施工组织设计",false,{"key":20,"text":21,"correct":14},"C","劳动力准备",{"key":23,"text":24,"correct":14},"D","物资准备",{"key":26,"text":27,"correct":18},"E","编制土建工程施工组织设计","ACD","P109-110 根据工程项目的性质不同，施工准备具体内容有比较大的区别，但总体上应有以下五个方面的内容一、技术准备二、工程准备。1.现场勘察。2.施工现场准备。三、物资准备。四、劳动力的准备。五、对外协作协调工作。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]