[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124403":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124403,791,2,"多选题","矿山施工调度工作基础是（ ），调度部门无权改变作业计划的内容。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工技术先进",false,{"key":16,"text":17,"correct":14},"B","施工管理严格",{"key":19,"text":20,"correct":21},"C","施工作业计划",true,{"key":23,"text":24,"correct":14},"D","施工作业规程",{"key":26,"text":27,"correct":21},"E","施工组织设计","CE","P252-253 矿山施工调工作基础是施工作业计划和施工组织设计，调度部门一般无权改变作业计划的内容。但在遇到特殊情况无法执行原计划时，可通过一定序，经技术部门同意进行调度工作。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]