[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124378":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124378,791,2,"多选题","矿业工程施工索赔的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期索赔",true,{"key":16,"text":17,"correct":18},"B","技术索赔",false,{"key":20,"text":21,"correct":14},"C","费用索赔",{"key":23,"text":24,"correct":18},"D","设备索赔",{"key":26,"text":27,"correct":18},"E","材料索赔","AC","P210-217 施工索赔的内容1.工期索赔矿业工程施工中，常常会发生一些未能预见的干扰事件使施工不能顺利进行，或使预定的施工计划受到干扰，最终造成工期延长，这样，对合同双方都会造成损失。由此可以提出期赔。施工单位提出工期索赔的目的通常有两个:是免去或推卸自己对已产生的工期延长合同责任，使自己不支付或尽可能不支付工期延长的罚款;二是进行因工期延长而造成的费用损失的索赔。2.费用索赔。矿业工程施工中，费用索赔的目的是承方为了弥补自己在承包工程中所发生的损失，或者为了弥补已经工程项目所支出的额外费用，还有可能是承包方为取得巳付出的劳动的报酬。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]