[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124375":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124375,791,2,"多选题","矿业工程施工合同变更的基本要求是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同变更在合同完全履行之后",false,{"key":16,"text":17,"correct":18},"B","合同变更是对原合同部分内容的变更或修改",true,{"key":20,"text":21,"correct":18},"C","合同变更一般需要有双方当事人的一致同意",{"key":23,"text":24,"correct":18},"D","合同变更须遵守法定的程序和形式",{"key":26,"text":27,"correct":14},"E","合同变更完全取消原来的债权债务关系","BCD","P207-210 合同变更的基本要求1.合同变更的期限为合同订立之后到合同没有完全履行之前。2.合同变更依据合同的存在而存在。3.合同变更是对原合同部分内容的变更或修改。4.合同变更一般需要有双方当事人的一致同意5.合同变更属于合法行为合同变更不得具有违法行为，违法协商变更的合同属于无效变更，不具有法律约束力。6.合同变更须遵守法定的程序和形式。《合同法》规定，经过当事人协商一致，可以变更合同按照行政法规要求，变更合同还应依据法律、行政法规的规定办理手续。7.合同变更并没有完全取消原来的债权债务关系，合同变更涉及的未履行的义务没有消失，没有履行义务的一方仍须承担不履行义务的责任。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]