[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124374":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124374,791,2,"多选题","工程索赔的一般程序是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","意向通知",true,{"key":16,"text":17,"correct":14},"B","提交索赔报告和有关资料",{"key":19,"text":20,"correct":14},"C","确定合理的补偿额",{"key":22,"text":23,"correct":14},"D","索赔报告评审",{"key":25,"text":26,"correct":27},"E","业主的索赔",false,"ABCD","P210-217 索赔程序：（1）意向通知首先由承包人发出索赔意向通知。承包人必须在索赔事件发生后的2 8 d内向工程师递交索赔意向通知，声明将对此事件索赔。（2）提交索赔报告和有关资料索赔意向通知提交后的2 8 d内，或业主（监理工程师同意的其他合理时间，承包人应递送正式的索赔报告。这是索赔程序中最重要的一环。（3）索赔报告评审接到承包人的索赔意向通知后，业主（监理工程师）应认真研究、审核承包人报送的索赔资料，以判定索赔是否成立，并在2 8 d内予以答复。（4）确定合理的补偿额",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]