[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124372":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124372,791,2,"多选题","矿业工程施工合同的变更可由（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","业主指示",true,{"key":16,"text":17,"correct":18},"B","业主申请",false,{"key":20,"text":21,"correct":18},"C","监理申请",{"key":23,"text":24,"correct":18},"D","承包商指示",{"key":26,"text":27,"correct":14},"E","承包商申请","AE","P207-210 合同变更的原因1.业主新的变更指令，对建筑的新要求。2.由于设计人员、监理人员、承包商事先没有很好地理解业主的意图，导致图纸修改。3.工程环境的变化，预定的工程条件不惟确，要求实施方案或实施计划变更。4.由于产生新技术新知识，有必要更改设计、原实施方案，或由于业主指令及业主责任的原因造成承包商施工方案改变。5.政府部门对工程新的要求。6.由于合同实施出现问题，必须调整合同目标或修改合同条款。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]