[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124362":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124362,791,2,"多选题","下列属于矿业工程项目招标承包内容的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","以矿井、洗煤厂的单项工程设计所包括的全部工程内容进行招标。",true,{"key":16,"text":17,"correct":18},"B","勘察设计的招标与承包",false,{"key":20,"text":21,"correct":14},"C","按施工组织设计规定的工程阶段进行招标",{"key":23,"text":24,"correct":18},"D","日常管理的招标与承包",{"key":26,"text":27,"correct":14},"E","已报建的在建项目应按可独立划分的工程进行招标","ACE","P196-197 根据矿业工程建设特点，从工程项目的角度可分为下列几种形式进行招标。1.以矿井、洗煤厂的单项工程设计所包括的全部工程内容进行招标。2.按施工组织设计规定的工程阶段进行招标，如施工准备、井筒、主巷道及硐室、洗煤厂、场内工业及公用建筑、生活区建筑、公路、铁路、通信、供水、供电等若干独立工程进行招标3.已报建的在建项目应按可独立划分的工程进行招标。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]