[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124337":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124337,791,2,"多选题","矿业工程项目竣工验收，应在施工单位自验、监理工程师初验合格的基础上，由建设单位组织，（ ）参加，在规定时间内进行正式验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","政府部门",false,{"key":16,"text":17,"correct":18},"B","设计单位",true,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","监理单位",{"key":26,"text":27,"correct":14},"E","检测单位","BCD","P156-158 建设单位收到工程验收报告后，应由建设单位负责人组织施工（含分包单位）、设计、监理等单位负责人进行单位工程验收。单位工程由分包单位施工时，分包单位对所承包的工程项目应按规定的程序检查评定，总包单位应派人员参加，分包工程完成后，应将工程有关资料交总包单位，建设单位验收合格，方可交付使用。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]