[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124330":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124330,791,2,"多选题","工程项目质量计划编制的依据有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工图纸、设计文件",true,{"key":16,"text":17,"correct":14},"B","国家法律法规、国家技术标准规范",{"key":19,"text":20,"correct":14},"C","施工企业项目管理规划大纲",{"key":22,"text":23,"correct":14},"D","工程的实际情况和特点",{"key":25,"text":26,"correct":27},"E","监理方的要求",false,"ABCD","P145-1146 依据'施工图纸、设计文件、国家法律法规、国家技术标准规范、施工企业项目管理规划大纲，结合工程的实际情况和特点，编制工程项目质量计划，编制的质量计划既要有综合计划，又要有分项目、分时期、分部门的具体计划，形成质量计划体系。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]