[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124326":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124326,791,2,"多选题","在矿山建设工程项目管理中，矿井建设的工期一般可采用下列（ ）方法来进行推算。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","根据矿井建设的关键线路来推算",true,{"key":16,"text":17,"correct":18},"B","根据安装工程的施工工期来推算",false,{"key":20,"text":21,"correct":14},"C","根据与矿建工程密切相连的土建和安装工程工期来推算",{"key":23,"text":24,"correct":14},"D","根据主要生产设备订货、到货和安装时间来推算",{"key":26,"text":27,"correct":18},"E","根据地面土建工程的施工时间来推算","ACD","P136-145 矿井建设的工期应当根据矿井建设的关键线路来推算具体推算时，又可以结合工程实施的情况，依据井巷工程的施工期来推算，或依据与井巷工程紧密相连的土建、安装工程施工期来推算，也可依照主要生产设备订货、到货和安装时间来推算。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]