[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124325":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124325,791,2,"多选题","与横道图计划相比，网络计划的主要优点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","形象、直观，且易于编制和理解",false,{"key":16,"text":17,"correct":18},"B","可以找出关键线路和关键工作",true,{"key":20,"text":21,"correct":18},"C","可以明确各项工作的机动时间",{"key":23,"text":24,"correct":18},"D","可以利用计算机进行计算、优化和调整",{"key":26,"text":27,"correct":18},"E","能明确表达各项工作之间的逻辑关系","BCDE","P128-131 利用网络图进度计划表示矿业工程的施工进度安排并进行进度控制，可以弥补横道图计划的许多不足。与横道图计划相比，网络图计划的主要特点是:（1）网络图'计划能够明确表达各项工作之间的逻辑关系。（2）通过网络计划时间参数的计算，可以找出关键线路和关键工作。（3）通过网络计划时间参数的计算，可以明确各项工作的机动时间。（4）网络图计划可以利用电子计算机进行计算、优化和调整。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]