[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124324":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124324,791,2,"多选题","当关键工作的实际进度较计划进度落后时，调整的目标就是采取措施将耽误的时问补回来，保证项目按期完成。调整的方法主要是缩短后续关键工作的持续时间，包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改变某些工作的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","增加某些工作的工作内容",false,{"key":20,"text":21,"correct":18},"C","减少某些工作的计划费用",{"key":23,"text":24,"correct":18},"D","改变某些工作的资源消耗",{"key":26,"text":27,"correct":14},"E","重新编制进度计划","AE","P133-136 根据对矿业工程进行计划执行情况检查，如果发生进度偏差，必须及时分析原因，并根据限制条件采用合理的调整方法。通常当施工进度偏差影响到后续工作和总工期时，应及时进行计划的调整。（1）重新安排后续关键工序的时间（2）改变后续工作的逻辑关系（3）重新编制施工进度计划",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]