[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124322":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124322,791,2,"多选题","矿业工程施工进度发生拖延后的控制措施，首先要分析引起拖延的原因，然后（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对引起进度拖延的原因采取措施",true,{"key":16,"text":17,"correct":14},"B","投入更多的资源加速活动",{"key":19,"text":20,"correct":21},"C","采取措施保证后续工作的施工质量",false,{"key":23,"text":24,"correct":21},"D","分析进度计划，减少工作内容",{"key":26,"text":27,"correct":14},"E","改进施工方法和技术，提高劳动生产率","ABE","P133-136 进度拖延的事后控制措施最关键的是要分析引起拖延的原因，通常有以下措施:（1）对引起进度拖延的原因采取措施;（2）投入更多的资源，加快施工进度;（3）采取措施保证后期工程的施工按计划执行;（4）分析进度网络，找出有工期延迟的路径;（5）征得业主的同意后，缩小工程的范围，包括减少工作量或删去一些工作包（或分项工程）；（6）改进方法和技术，提高劳动生产率;（7）采用外包策略，让更专业的公司用更快的速度、更低的成本完成一些分项工程。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]