[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124321":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124321,791,2,"多选题","某施工单位承担一矿井井底车场主要巷道的掘进施工任务。所编制的施工进度计划见图2G320030-2，施工单位在工作H的施工中，由于不可预见地质因素造成工作面冒顶事故，处理事故耽误工期10d。由于发生冒顶事故，工作H发生工期拖延后，造成工作I的工期拖延10d，那么（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该工程的总工期不会改变",false,{"key":16,"text":17,"correct":18},"B","该工程的总工期会拖延10d",true,{"key":20,"text":21,"correct":18},"C","工作C有了机动时间",{"key":23,"text":24,"correct":18},"D","网络计划的关键线路发生变化",{"key":26,"text":27,"correct":14},"E","网络计划需要重新规划和调整","BCD","P127-128 施工单位编制的网络进度计划的关键线路为D→E→G→C(或①→③→④→⑤→⑥→⑧)，计算工期为30+150+30+30＝240d。在施工中H处理事故耽误10d，由于H发生工期拖延，造成工作I的工期拖延10d，故网络计划的关键线路发生变化，关键线路变为D→E→H→I(或①→③→④→⑦→⑧)，计算工期为30+150+30+10+20+10＝250d。工作C有了机动时间10d。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]