[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124320":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124320,791,2,"多选题","加快井巷工程关键路线施工速度的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","全面規划,统筹安排,综合平衡",true,{"key":16,"text":17,"correct":14},"B","采取平行交叉作业方法",{"key":19,"text":20,"correct":21},"C","合理制定井巷施工进度指标",false,{"key":23,"text":24,"correct":14},"D","优选重点队伍施工关键工作",{"key":26,"text":27,"correct":14},"E","采用新工艺、新技术、新装备,提高井巷工程单进水平","ABDE","P136-145 加快井巷工程关键路线施工速度的具体措施：1.全面规划，统筹安排。特别要仔细安排矿、土、安相互交叉影响较大的工序内容。2.充分重视安装工程施工，并尽量提前利用永久设备，对提高施工能力也是非常有益的。3采取多头作业、平行交叉作业，积极采用新技术、新工艺、新装备，提高井巷工程单进水平。4.把施工水平高、装备精良的重点掘进队放在关键路线上，为快速施工创造条件。5.充分做好各项施工准备工作，减少施工准备占用时间，降低辅助生产占用的工时。6.加强综合平衡，做好工序间的衔接，解决薄弱环节;利用网络技术做好动态管理，适时调整各项单位工程进度。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]