[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124309":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124309,791,2,"多选题","井筒表土普通施工法包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","井圈背板普通施工法",true,{"key":16,"text":17,"correct":14},"B","吊挂井壁施工法",{"key":19,"text":20,"correct":14},"C","板桩施工法",{"key":22,"text":23,"correct":24},"D","表土降水施工法",false,{"key":26,"text":27,"correct":24},"E","冻结施工法","ABC","P65-67 井筒表土普通施工法1.井圈背板普通施工法：是采用人工或抓岩机（土硬时可放小炮）出土，下掘一小段后（空帮距根据土层的稳定性来确定，一般不超过1.2m），用井圈、背板进行时支护，掘进一长段后（一般不超过3 0 m），再由下向上拆除井圈、背板，然后砌筑永久井壁。此周而复始，直至基岩。这种方法适用于较稳定的土层。2.吊挂井壁施工法：吊挂井壁施工法是用于稳定性较差的土层中的一种短段掘砌施工方法。3.板桩施工法：对于厚度不大的不稳定表土层，在开挖之前，可先用人工或打桩机在工作面或地面沿井筒荒径依次打人一圈板桩，形成一四周密封的圆筒，用以支承井壁，并在它的保护下进行掘进。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]