[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124305":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124305,791,2,"多选题","立井井筒施工时布置在井筒内的凿井设施主要包括有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","封口盘",false,{"key":16,"text":17,"correct":14},"B","翻矸台",{"key":19,"text":20,"correct":14},"C","保护盘",{"key":22,"text":23,"correct":24},"D","吊盘",true,{"key":26,"text":27,"correct":24},"E","固定盘","DE","P79-81 凿井期间，提升容器以肝石吊桶为主，有时也采用底卸式下料吊桶和下料筐等容器。当转人车场和巷道施工时，提升容器则由吊桶改为罐笼。立井开凿时年，为了悬挂吊盘、砌壁模板、安全梯、吊泵和一系列管路缆线，必须合理选用相应的悬吊设备。悬吊系统由钢丝绳、天轮及凿井绞车等组成。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]