[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124304":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124304,791,2,"多选题","立井井筒施工时需要布置的凿井设施主要包括有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","吊盘",true,{"key":16,"text":17,"correct":18},"B","保护盘",false,{"key":20,"text":21,"correct":14},"C","固定盘",{"key":23,"text":24,"correct":14},"D","封口盘",{"key":26,"text":27,"correct":14},"E","翻矸台","ACDE","P79-81 立井井筒施工时，为了满足掘进提升、翻卸矸石、砌筑井壁和悬吊井内施工设备、设施的需要，还需布置凿井井架、卸矸台、封口盘、固定盘、吊盘、提升机和凿井绞车等施工设备或设施，这些设备和设施的选用和布置要根据施工条件进行计算。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]