[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124300":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124300,791,2,"多选题","立井井筒施工时可选择的排水方案有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","吊桶排水",true,{"key":16,"text":17,"correct":14},"B","吊泵排水",{"key":19,"text":20,"correct":21},"C","压气排水系统",false,{"key":23,"text":24,"correct":14},"D","风动潜水泵配合吊泵进行排水",{"key":26,"text":27,"correct":14},"E","卧泵排水","ABDE","P76-77 根据井筒涌水量大小不同，工作面积水的排出方法可分为吊桶排水和吊泵或卧泵排水。泵排水时还可以与风动潜水泵进行配套排水",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]