[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124285":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124285,791,2,"多选题","立井井筒施工中井筒内应布置（ ），用于突发涌水情况下的排水工作。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","吊桶",false,{"key":16,"text":17,"correct":14},"B","潜水泵",{"key":19,"text":20,"correct":21},"C","吊泵",true,{"key":23,"text":24,"correct":21},"D","卧泵",{"key":26,"text":27,"correct":14},"E","压力泵","CD","P78-79 井筒施工时，工作面的积水必须及时进行排除，当井简涌水量小于8m3\u002Fh，可用吊桶排水，即用隔膜泵或潜水泵将工作面积水排入吊桶，充满矸石空隙，随同矸石提升排出地面。当涌水量较大，可设置吊泵、卧泵进行排水。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]