[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124282":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124282,791,2,"多选题","通常立井井筒基岩段含水层的处理方法包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","地面预注浆",true,{"key":16,"text":17,"correct":14},"B","工作面预注浆",{"key":19,"text":20,"correct":21},"C","壁后注浆",false,{"key":23,"text":24,"correct":21},"D","利用泄水管泄水",{"key":26,"text":27,"correct":21},"E","布置吊泵排水","AB","P76-77 注浆堵水有两种方法:一种是为了打干井而在井筒掘进前向围岩含水层注浆堵水，这种注浆方法称为预注浆;另一种是为了封住井壁渗水而在井筒掘砌完后向含水层段的井壁注浆，这种注浆法称为壁后注浆。（一）预注浆1.地面预注浆。2.工作面预注浆。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]