[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124281":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124281,791,2,"多选题","下列关于注浆法说法中，正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","根据注浆工作与井巷掘进工序的先后时间次序进行分类，注浆法分为预注浆法和壁后注浆法",true,{"key":16,"text":17,"correct":14},"B","预注浆法是在凿井前或在井筒掘进到含水层之前所进行的注浆工作",{"key":19,"text":20,"correct":14},"C","后注浆法是在井巷掘砌之后所进行的注浆工作",{"key":22,"text":23,"correct":24},"D","预注浆往往是为了减少井筒涌水，杜绝井壁和井帮的渗水和加强永久支护采取的治水措施",false,{"key":26,"text":27,"correct":14},"E","注浆法既可用于为了减少井筒涌水，加快凿井速度、对井筒全深范围内的所有含水层进行预注浆“打干井”施工，又可对裂隙含水岩层和松散砂土层进行堵水、加固","ABCE","P76-77 注浆堵水有两种方法:一种是为了打干井而在井筒掘进前向围岩含水层注浆堵水，这种注浆方法称为预注浆;另一种是为了封住井壁渗水而在井筒掘砌完后向含水层段的井壁注浆，这种注浆法称为壁后注浆。（一）预注浆1.地面预注浆。2.工作面预注浆。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]