[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124259":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124259,791,2,"多选题","为提高工作效率，推土机工作时可采用的施工方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","下坡推土",true,{"key":16,"text":17,"correct":18},"B","上坡推土",false,{"key":20,"text":21,"correct":14},"C","并列推土",{"key":23,"text":24,"correct":18},"D","侧向推土",{"key":26,"text":27,"correct":14},"E","槽形推土","ACE","P58-59 提高推土机的生产率，可采用下述方法:1.槽形推土。推土机多次在一条作业线上工作，使地面形成一条浅槽，以减少从铲刀两散漏。这样作业可增加推土量10%-30%。槽深以1m左右为宜，槽问土埂宽约0.5 m。在推出多条槽后，再将土埂推人槽内，然后运出。 2.下坡推土。在斜坡上方顺下坡方向工作。坡度不宜大于1 5°，以免后退时爬坡困难。 3.并列推土。在大面积场地平整时，可采用多台推土机并列作业。通常两机并列推土可增大推土量15%-30%，三机并列惟士可增加30%-40%。并列推土的运距宜为20-60m。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]