[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124204,791,2,"多选题","关于建立矿区施工测量控制网的主要工作，说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","进行施工测量控制网的设计，确定包括精度、布网形式等内容",true,{"key":16,"text":17,"correct":14},"B","编制操作规范，包括使用的仪器及相关规程",{"key":19,"text":20,"correct":21},"C","在地图上选点，并按图上的点在实地埋桩",false,{"key":23,"text":24,"correct":21},"D","诸多桩点的连线就可以形成测量网",{"key":26,"text":27,"correct":21},"E","导入建筑物各细部的位置、形状等，完成控制网工作","AB","P1-4 施工控制网布设的基本程序:（1）确定等级和精度要求;（2）确定布网形式;（3）确定测量仪器和操作规范;（4）通过图上选点构网到实地探勘;（5）埋点;（6）外业观测;（7）内业处理;（8）形成成果。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]