[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124134":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124134,791,2,"多选题","尾矿库使用达到设计标高时应进行闭库处理，有关闭库的规定为（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","尾矿库使用到最终设计高程前2~3年，应进行闭库设计",true,{"key":16,"text":17,"correct":18},"B","尾矿库闭库设计和闭库施工方案应由当地矿山安全生产管理部门进行审查 通过",false,{"key":20,"text":21,"correct":14},"C","尾矿库闭库设计和闭库施工方案，未经省级以上安全生产监督管理部门审查或 审査不合格的，企业不得进行尾矿库闭库施工",{"key":23,"text":24,"correct":14},"D","尾矿库闭库工程结束后，必须报省级以上安全生产监督管理部门组织安全验 收，验收合格后方可关闭尾矿库",{"key":26,"text":27,"correct":14},"E","未经安全生产监督管理部门验收或验收不合格的，企业不得关闭尾矿库","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]