[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124111":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124111,791,2,"多选题","关于井巷施工遇到突出煤层时，采掘作业的规定，以下说法正确的是（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","严禁采用水力采煤法、倒台阶采煤法及其他非正规采煤法",true,{"key":16,"text":17,"correct":14},"B","急倾斜煤层适合采用伪倾斜正台阶、掩护支架采煤法",{"key":19,"text":20,"correct":14},"C","急倾斜煤层掘进上山时，采用双上山或伪倾斜上山等掘进方式，并加强支护",{"key":22,"text":23,"correct":24},"D","掘进工作面与煤层巷道交叉贯通前，被贯通的煤层巷道必须超过贯通位置，其超前距不得小于3 m，并且贯通点周围5 m内的巷道应加强支护。在掘进工作面与被贯通巷道距离小于40m的作业期间，被贯通巷道内不得安排作业，并保持正常通风，且在放炮时不得有人",false,{"key":26,"text":27,"correct":14},"E","采煤工作面尽可能采用刨煤机或浅截深采煤机采煤","ABCE","掘进工作面与煤层巷道交叉贯通前，被贯通的煤层巷道必须超过贯通位置，其超前距不得小于5 m，并且贯通点周围10 m内的巷道应加强支护。在掘进工作面与被贯通巷道距离小于60m的作业期间，被贯通巷道内不得安排作业，并保持正常通风，且在放炮时不得有人。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]