[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124072":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124072,791,2,"多选题","下列关于三类工程综合平衡的论述，正确的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","应围绕关键线路的关键工程组织快速施工",true,{"key":16,"text":17,"correct":14},"B","一般情况下，矿建工程项目构成矿井建设的关键线路",{"key":19,"text":20,"correct":21},"C","关键线路和关键工程在任何情况下都是固定的",false,{"key":23,"text":24,"correct":21},"D","矿建、土建和安装工作应齐头并进，同时进行",{"key":26,"text":27,"correct":14},"E","井筒到底后，巷道开拓和地面建筑及机电设备安装工程将成为关键","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]