[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124071":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124071,791,2,"多选题","三类工程综合平衡的具体工作内容是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","全面规划，合理安排",true,{"key":16,"text":17,"correct":18},"B","矿建工程为主，土建和机电安装工程为辅",false,{"key":20,"text":21,"correct":14},"C","采用先进的技术和工艺，制订周密的施工方案",{"key":23,"text":24,"correct":18},"D","矿建工程结束后，以土建工程作为重点",{"key":26,"text":27,"correct":14},"E","精心组织施工，搞好综合平衡","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]