[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124067":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124067,791,2,"多选题","矿业工程施工技术方案的具体确定，在选择时应考虑到（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工准备期应以安排井筒开工以及项目所需要的准备工作为主",true,{"key":16,"text":17,"correct":14},"B","建井主要矛盾线上关键工程的施工方法",{"key":19,"text":20,"correct":21},"C","建井初期应重视地面土建工程施工以提供良好的生活条件",false,{"key":23,"text":24,"correct":21},"D","投入生产前应保证所有项目全部完工",{"key":26,"text":27,"correct":14},"E","矿井机电设备安装工程的安排应以保证项目联合试运转之前完成为原则","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]