[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124061":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124061,791,2,"多选题","某矿建公司通过招投标方式承担了一直径为5m的立井井筒的施工任务，由于该 井筒表土层水量较大，需要冻结。总施工工期为15个月，关于15个月的总施工工期，正 确的表述是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","所有关键工程的工期相加",false,{"key":16,"text":17,"correct":14},"B","所有关键线路的工期相加",{"key":19,"text":20,"correct":21},"C","关键线路的持续时间",true,{"key":23,"text":24,"correct":21},"D","持续时间最长的线路的时间",{"key":26,"text":27,"correct":14},"E","所有工作的时间之和","CD","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]