[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124051":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124051,791,2,"多选题","矿业工程项目现场管理有关提升运输系统管理的主要内容包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立完善的提升机房管理制度",true,{"key":16,"text":17,"correct":18},"B","建立严格的提升机运行制度",false,{"key":20,"text":21,"correct":14},"C","严格遵循提升机房的管理制度",{"key":23,"text":24,"correct":18},"D","严格遵照规范井下设备的管理",{"key":26,"text":27,"correct":14},"E","落实提升系统的安全、正常运行措施","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]