[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124026":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124026,791,2,"多选题","矿业工程施工中，可能引起承包商进行施工索赔的主要原因包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主项目手续不全",true,{"key":16,"text":17,"correct":14},"B","设计变更",{"key":19,"text":20,"correct":21},"C","施工单位手续不全",false,{"key":23,"text":24,"correct":21},"D","施工方案失当",{"key":26,"text":27,"correct":14},"E","不可抗力","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]