[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124021":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124021,791,2,"多选题","矿业工程施工合同变更的范围可涉及（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同中任何工作工程量的改变",true,{"key":16,"text":17,"correct":14},"B","工作质量或其他特性的变更",{"key":19,"text":20,"correct":21},"C","工程项目任何结构的改变",false,{"key":23,"text":24,"correct":14},"D","改变原定的施工顺序或时间安排",{"key":26,"text":27,"correct":21},"E","改变合同约定的工作内容","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]