[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124015":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124015,791,2,"多选题","关于开标和决标，以下说法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标人应当确定投标人编制投标文件所需要的合理时间；但是，依法必须进行招标的项目，自招标文件开始发出之日起至投标人提交投标文件截止之日止，最短不得少于三十日",false,{"key":16,"text":17,"correct":18},"B","招标人根据招标项目的具体情况，可以组织潜在投标人踏勘项目现场，向其介绍工程场地和相关环境的有关情况。潜在投标人依据招标人介绍情况作出的判断和决策，由投标人自行负责",true,{"key":20,"text":21,"correct":18},"C","招标人不得单独或者分别组织任何一个投标人进行现场踏勘",{"key":23,"text":24,"correct":18},"D","对于潜在投标人在阅读招标文件和现场踏勘中提出的疑问，招标人可以书面形式或召开投标预备会的方式解答，但需同时将解答以书面方式通知所有购买招标文件的潜在投标人。该解答的内容为招标文件的组成部分",{"key":26,"text":27,"correct":18},"E","招标人可根据项目特点决定是否编制标底。编制标底的，标底编制过程和标底在开标前必须保密","BCDE","招标人应当确定投标人编制投标文件所需要的合理时间；但是，依法必须进行招标的项目，自招标文件开始发出之日起至投标人提交投标文件截止之日止，最短不得少于二十日。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]