[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1124005,791,2,"多选题","关于矿山工程项目工作量变更的确定原则，下列说法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程量清单漏项或由于设计变更引起新的工程量清单项目，其相应综合单价 由承包方提出，经发包人确认后作为结算的依据",true,{"key":16,"text":17,"correct":18},"B","由于设计变更引起工程量增减部分，均应执行新的综合单价",false,{"key":20,"text":21,"correct":14},"C","增减的工程量属合同约定幅度以外的，其综合单价由承包人提出，经发包人确 认后作为结算的依据",{"key":23,"text":24,"correct":14},"D","如合同另有约定，应按照合同规定确定",{"key":26,"text":27,"correct":14},"E","由于工程量的变更，且实际发生了规定以外的费用损失，承包人可提出索赔要 求，与发包人协商确认后，给予补偿","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]