[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123998,791,2,"多选题","关于锚杆的张拉与施加预应力(锁定)的规定，以下说法正确的是（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","锚固段强度大于15MPa并达到设计强度等级的75%后方可进行张拉",true,{"key":16,"text":17,"correct":14},"B","锚杆张拉顺序应考虑对邻近锚杆的影响",{"key":19,"text":20,"correct":14},"C","锚杆宜张拉至设计荷载的0. 9~1. 0倍后，再按设计要求锁定",{"key":22,"text":23,"correct":14},"D","锚杆张拉控制应力不应超过锚杆杆体强度标准值的0.75倍",{"key":25,"text":26,"correct":27},"E","锚固段强度大于15MPa并达到设计强度等级的50%后方可进行张拉",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]