[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123996":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123996,791,2,"多选题","该井筒工程竣工后应检查的内容有（）等。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","井筒中心坐标、井口标高、井筒的深度以及与井筒连接的各水平或倾斜的巷 道口的标高和方位",true,{"key":16,"text":17,"correct":14},"B","井壁的质量和井筒的总漏水量，一昼夜应测漏水量3次，取其平均值",{"key":19,"text":20,"correct":14},"C","井筒的断面和井壁的垂直程度",{"key":22,"text":23,"correct":14},"D","隐蔽工程记录、材料和试块的试验报告",{"key":25,"text":26,"correct":27},"E","设计单位提供的井筒的平面布置图，包括井筒的中心坐标、井口标高，与十字 线方向方位",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]