[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123977":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123977,791,2,"多选题","所有检验批和分项工程均应由（）组织验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":18},"B","监理工程师",true,{"key":20,"text":21,"correct":18},"C","建设单位项目负责人",{"key":23,"text":24,"correct":14},"D","专业施工人员",{"key":26,"text":27,"correct":14},"E","设计人员","BC","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]