[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123965":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123965,791,2,"多选题","关于网络图计划的主要特点，以下说法正确的是（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","网络图计划能够明确表达各项工作之间的逻辑关系",true,{"key":16,"text":17,"correct":14},"B","通过网络计划时间参数的计算，可以找出关键线路和关键工作",{"key":19,"text":20,"correct":14},"C","通过网络计划时间参数的计算，可以明确各项工作的机动时间",{"key":22,"text":23,"correct":14},"D","网络图计划可以利用电子计算机进行计算、优化和调整",{"key":25,"text":26,"correct":27},"E","不能明确地反映出影响工期的关键工作和关键线路，也就无法反映出整个工程项",false,"ABCD","选项E所描述的内容，是横道图的缺点。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]