[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123964":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":21,"analysis":22},1123964,791,2,"多选题","施工单位施工网络图如图,在H：作H的施工中，造成工作面冒顶事 故，处理事故耽误工期10天。由于发生冒顶事故，作为施工单位，在后续工作安排上重 点注意的工程是（）》",[11,15,18],{"key":12,"text":13,"correct":14},"A","G",true,{"key":16,"text":17,"correct":14},"B","H",{"key":19,"text":20,"correct":14},"C","I","ABC","",{"id":6,"name":24,"category":25,"favorite":26},"二建矿业工程实务","建筑工程",0]