[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123963":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123963,791,2,"多选题","某施工单位承担一矿井井底车场主要巷道的掘进施工任务。所编制的施工进度计 划见图2G320030-2，施工单位在工作H的施工中，由于不可预见地质因素造成工作面冒 顶事故，处理事故耽误工期10天。由于发生冒顶事故，工作H发生工期拖延后，造成工 作I的工期拖延10天，那么（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该工程的总工期不会改变",false,{"key":16,"text":17,"correct":18},"B","该工程的总工期会拖延10天",true,{"key":20,"text":21,"correct":18},"C","工作",{"key":23,"text":24,"correct":18},"D","D有了机动时间",{"key":26,"text":27,"correct":14},"E","网络计划的关键线路发生变化","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]